MSU Stadium Expansion Plan <– Click to see the video

Included are six phases:

A. It should first be mentioned that MSU is installing FieldTurf as we speak.
1. 38 new skysuites over the student side bleachers.
2. Replace the south endzone bleachers with a bowl, in total adding about 600 seats (getting rid of those rickity bleachers we currently have).
3. Upper bowl of south endzone (adding 3,730 seats).
4. Rebuild east (student) grandstand, adding 3800 seats and removing 6000.
5. Lower bowl of north endzone, adding 2,630 seats.
6. Upper bowl of north endzone, adding 3,730 seats.

New capacity will be approximately 22,00, and is schedule to be completed over the course of about 10 years.